Thursday afternoon brought the plumbing inspector around. We didn't pass plumbing (yet) because the contractor replaced all the plumbing in the kids' bathroom (not the original plan), and we needed to add that to our permit. Also, the plumbing inspector wanted to see the fireplace permit, and the fireplace company "forgot" to file it (though they did not forget to charge us the $300 permit fee), so we had to get them to complete that task. We get a redo tomorrow.
Electrical inspection went smoothly on Friday, though the inspector wants "load calcs" to show that we have enough electrical capacity (gulp).
Insulation inspection was today, we passed that one. After the plumbing inspection do-over tomorrow, we'll be ready for drywall!
Next big inspection after this week will be the final inspection!
Contractor is estimating completion at the end of February, but I'm still managing my expectations and planning for March completion. :)